K.S.A. 75-3002 establishes the state fiscal year as commencing on the first
day of July in each year and closing on the thirtieth day of June of the
succeeding year. However, to allow state agencies time to process as much old
year business as possible, the old year records remain open through the second
Monday of July (PPM No. 14,002). For the fiscal year 2002 closing, that date has
been extended to Wednesday, July 10, 2002. During this period the Statewide
Accounting and Reporting System (STARS) processes old and new fiscal year
business concurrently.
The workload both at your agency and the Division of Accounts and Reports is
greatly increased during the fiscal year end closing period. We ask that you use
the following reminders and guidelines to help facilitate the fiscal year end
processing.
April 17 |
Letter advising agencies to prepare Real Estate Encumbrance
Renewals (affected agencies only). |
May 21 |
Letter requesting agencies to review outstanding encumbrances. |
May 23 |
Year-end closing information at ASTRA meeting. |
June 3 |
Annual review of housing, food service and other employee maintenance
rates (DA-171). |
June 3 |
Agencies may begin entering on-line DA-118 transactions. |
June 14 |
Fiscal year 2003 valid funds tape and valid PCA tape sent to State
Treasurer. |
June 17 |
Preliminary fiscal year 2003 Central Chart of Accounts mailed
to agencies. |
June 17 |
Accounts and Reports, Payroll Services will insert a new row
in the SHARP department budget tables effective
dated June 9, 2002 which reflect a budget end date of June 8, 2003 and fiscal
year of 2003. |
June 17 |
Process payroll encumbrances for Friday, June 21 on-cycle pay
date (last FY2002 on-cycle). |
June 18 |
Informational Circular to all agencies regarding fiscal year
rate changes in payroll deductions and contributions. |
June 21 |
Review any outstanding checks and process paycheck reversals
prior to June 24, 2002, which is the last off-cycle payroll charged to FY2002.
Any checks issued in this cycle will be dated June 27, 2002 and charged to
FY2002. |
June 21 |
Liquidate payroll encumbrances for the on-cycle pay date of
June 21. |
June 24 |
Last payroll off-cycle to be run for FY2002 transactions and
will have a paycheck date of June 27, 2002. |
June 25 |
Process payroll accounting transactions created for true EFT
reversals and cancelled checks and encumbrances from the June 24 off-cycle. |
June 27 |
Liquidate encumbrances for the Monday, June 24 payroll off-cycle. |
June 28 |
Regents establish Payroll Clearing Fund indexes in STARS for
FY2003. |
June 28 |
Updates to payroll position pool definitions for FY2003 must
be entered into SHARP by 5:00 P.M. in order to be reflected
in the charges for the on-cycle paychecks dated July 5, 2002 (first on-cycle
paychecks charged to FY2003). Updates should be entered with an effective
date of June 10, 2002. |
July 1 |
FY2003 transactions accepted for processing; beginning of concurrent
processing period for final fiscal year 2002 transactions; fiscal year 2003
appropriation transactions loaded in STARS nightly cycle. |
July 1 |
SOKI3+ system allows FY2003 transactions
beginning at 8:00 A.M. |
July 2 |
On-line entry of STARS expenditures against BFY2003 appropriated
and limited funds; FY2003 appropriation transactions process in the July 1st
STARS nightly batch cycle. |
July 2 |
Process payroll encumbrances for the Friday, July 5 on-cycle
paycheck date and encumbrances from the July 1 off-cycle; process accounting
transactions created for true EFT reversals and cancelled checks from the
July 1 off-cycle. |
July 3 |
Final FY2002 credit card receipts and credit card clearing fund
fees and charges processed by the State Treasurer. |
July 5 |
Liquidate payroll encumbrances for the July 5 on-cycle paycheck
date and July 1 off-cycle; process accounting transactions created for true
EFT reversals and cancelled checks and encumbrances from the July 3 off-cycle. |
July 8 |
DA-35 electronic files (prior period funding Payroll adjustments)
must be received by 5:00 P.M. |
July 9 |
Liquidate encumbrances for the July 3 payroll off-cycle (checks
dated July 9). |
July 10 |
State Treasurer accepts final fiscal year 2002 receipt vouchers
from agencies until 3:00 P.M. |
July 10 |
SOKI3+ receipt documents for FY 2002
must be entered by 3:00 P.M for final fiscal year 2002 receipt transactions. |
July 10 |
Electronic transmission of FY2002 expenditure and encumbrance
datasets to BDAS must occur by noon. Supporting batched documents must be
received in the Central Accounting Services Section by 5:00 P.M. |
July 10 |
Central Accounting Services Section accepts final expenditure
and encumbrance batches (including DA-118 batches submitted for data entry)
from agencies for FY2002 until 5:00 P.M. No firm encumbrances are allowed
for State General Fund. |
July 10 |
Agencies entering STARS payment vouchers on-line (not dataset)
must have final documents for fiscal year 2002 entered by 5:00 P.M. |
July 10 |
SOKI3+ journal voucher and interfund
voucher documents for FY 2002 must be entered by 5:00 P.M. |
July 11 |
Agencies entering payment vouchers on-line (not dataset) in
STARS with a June effective date must have paper documents into the Central
Accounting Services Section by 12:00 noon to avoid transactions being deleted
from STARS. Vouchers processed under delegated audit authority should be released
by the agency by 12:00 noon. |
July 11 |
SOKI3+ closed to agency users. (JV,
IFV and Order Modules) |
July 11 |
SOKI3+ open for FY2003 receipts. |
July 11 |
Final FY 2002 SOKI3+ upload to STARS. |
July 12 |
SOKI3+ open for all FY2003 transactions. |
July 15 |
Agencies may enter DA-118's on-line (not dataset) until 5:00
P.M. No firm encumbrances are allowed for State General Fund. |
July 16 |
Agencies entering DA-118's on-line (not dataset) must have paper
documents delivered to the Central Accounting Services Section by 12:00 noon
to avoid transactions being deleted from STARS. |
July 17 |
Final processing of June 2002 transactions expected; end of
the concurrent processing period (STARS will be open to Accounts and Reports
Staff only). |
July 18 |
Begin processing for monthly and annual reports and statements,
processing of closing and opening entries and preparation of opening and closing
transaction reports. |
July 22 |
June 2002 monthly STARS reports expected to be mailed to agencies. |
July 22 |
Resume processing of July 2002 (FY2003) transactions. |
July 26 |
FY2002 closing reports and FY2003 opening reports expected to
be mailed to agencies. |
August 5 |
DA-404, DA-406 and DA-410 STARS Budget Worksheets. |
September 30 |
Updates to the Master List of Real Property and Form DA-87, Annual
Capital Asset Reporting, due in Accounts and Reports. |